New bacteria limits force Monterey One Water to revisit RTP upgrade
Monterey One Water, California · Meeting date: November 20, 2026 · Published: November 23, 2026
A proposed NPDES permit would end Monterey One Water’s ability to discharge undisinfected secondary effluent to Monterey Bay, prompting a $164,359 disinfection alternatives study. The utility will compare ultraviolet, peracetic acid and membrane bioreactor options as it works towards a wider treatment-plant upgrade.
Key points
- The Central Coast Regional Water Quality Control Board’s proposed permit would impose bacteria limits on Regional Treatment Plant effluent, requiring disinfection before ocean discharge.
- Monterey One Water plans to engage Black & Veatch for a $164,359 alternatives analysis comparing BNR plus UV, BNR plus peracetic acid, and membrane bioreactor treatment.
- Draft compliance orders require completion of the analysis and master-plan update by 1 July 2028; Monterey One Water proposed full compliance by 31 December 2037.
- The 29.6mgd Regional Treatment Plant currently discharges treated but undisinfected wastewater through a deep ocean outfall.
Full report
Monterey One Water is preparing to add disinfection to the planned upgrade of its 29.6mgd Regional Treatment Plant after the Central Coast Regional Water Quality Control Board proposed new bacteria limits for the facility’s ocean discharge.
The change would be consequential for the Monterey County wastewater utility, whose Regional Treatment Plant has long discharged treated but undisinfected secondary effluent through a deep ocean outfall. Monterey One Water has relied on extensive receiving-water monitoring to demonstrate that bacteria decay before reaching nearshore recreation and shellfish-harvesting areas.
The proposed NPDES permit instead places emphasis on bacteria limits at the end of the pipe. Staff said the shift followed a 2025 US Supreme Court decision that led the water board to replace receiving-water limits with effluent limits. The permit would require disinfection of all treated secondary effluent before discharge to Monterey Bay.
Monterey One Water is therefore seeking to update the master plan for a major RTP upgrade, accepted by its board in April 2026. The original plan selected biological nutrient removal (BNR), in part because it could reuse refurbished primary and secondary clarifiers. A membrane bioreactor (MBR) ranked closely behind it, but carried capital and operating costs estimated at about 10% higher than BNR.
Staff outlined a proposed $164,359 professional-services agreement with Black & Veatch to assess three routes: BNR with ultraviolet disinfection; BNR with peracetic acid dosing; and MBR treatment, using membrane filtration to remove bacteria. The study is also intended to quantify whether the higher-quality MBR effluent could reduce treatment needs at Monterey One Water’s Salinas Valley Reclamation Project and Advanced Water Purification Facility.
That question has financial and operational significance. Staff noted that MBR-quality effluent could eliminate coagulation, flocculation and filtration at the reclamation project, while reducing ozone and sulfuric-acid needs at the purification facility. Committee members also asked staff to examine how costs and benefits should be allocated if upgraded treatment provides benefits to the recycled-water operations.
Draft time-schedule orders issued by the water board would shield Monterey One Water from penalties for violating the new bacteria limits while it advances compliance actions. They require the disinfection alternatives analysis and master-plan update by 1 July 2028. Monterey One Water said it intends to complete the work within six months, ahead of preliminary engineering planned for 2027.
The utility requested a compliance schedule extending to 31 December 2037 for completion of the wider RTP upgrade. It said the regional board’s executive officer had acknowledged that projects of this scale can take up to 10 years, although the draft orders set out an initial five-year schedule under state compliance-policy constraints.