Mission Springs unlocks $5.4m septic-to-sewer programme with Army agreement
Mission Springs Water District, California · Meeting date: November 16, 2026 · Published: November 17, 2026
Mission Springs Water District has approved a Department of the Army design-and-construction agreement for GQPP Area J-2-1, advancing a gravity sewer collection system intended to enable up to 354 parcels to discontinue septic use. The action lifts the project budget from $420,000 to $5.4 million.
Key points
- The board unanimously approved a $4.98 million budget augmentation for Job 11472, Area J-2, taking the capital budget to $5.4 million.
- The first increment covers design updates, environmental documentation and construction of a gravity sewer collection system in GQPP Area J-2-1.
- MSWD said it had secured $3.5 million in federal funding and would provide a $1.166667 million match; costs incurred by the district are to be reimbursed through Assessment District 18.
- The initial works are intended to allow up to 354 parcels in Assessment District 18 to replace septic systems with sewer service.
Full report
Mission Springs Water District has moved to restart a long-delayed septic-to-sewer extension in the Mission Creek Subbasin, approving a Department of the Army agreement and a $4.98 million capital-budget augmentation for Groundwater Quality Protection Program Area J-2-1.
The unanimous November 16 decision increases the budget for Job 11472, Area J-2, from $420,000 to $5.4 million. The initial increment will update a 2010 design, complete environmental documentation and construct a gravity sanitary sewer collection system. It is intended to enable up to 354 parcels within Assessment District 18 to discontinue septic use.
The project is part of MSWD's Groundwater Quality Protection Program, which targets septic systems overlying the Mission Creek, Desert Hot Springs and Indio subbasins of the Coachella Valley Groundwater Basin. The programme is intended to eliminate known pollution sources affecting groundwater supplies.
MSWD's engineering manager said the J-2-1 designation is not a fixed geographic subset of Area J-2. Instead, it allows the district to determine the final extent of construction after design work establishes the funds remaining for construction. The northern portion of the project area is expected to be undertaken first, with a southern portion to be added if funds remain.
The district said it had secured $3.5 million in federal funding through the Army Corps of Engineers, while MSWD's matching share is $1.166667 million. Staff also estimates $733,333 for the final initial study-mitigated negative declaration completed in June 2026 and construction-support services. MSWD said its costs will be reimbursed through assessments on the 354 parcels in Assessment District 18.
Under the Army agreement, the initial work is projected to involve a 75% federal and 25% non-federal cost share. The associated letter report places the first increment's expected completion within 39 months of approval of the project agreement and letter report.
General Manager Brian Macy said the district had also received state funding to complete phase two of the M-2 project. The award did not include requested funding for a water line or a road around the Nancy Wright facility, but Macy said it would cover planned sewer works and private-property abatements in M-2. He added that $900,000 currently targeted to M-2 could potentially be redirected to expand J-2 work if engineering progresses quickly enough.
Future GQPP increments could include sewer collection systems in Areas J-2-2 through J-2-4, H, I and K, subject to federal and state funding allocations.
This summary was generated by AI based on the source document and may contain errors.