Los Angeles awards $14.75m Westlake Relief Drain rehabilitation contract
LA Sanitation & Environment, California · Meeting date: November 20, 2026 · Published: November 23, 2026
The Board of Public Works unanimously awarded Spiniello Infrastructure West a 730-calendar-day contract for Unit 5 of the Westlake Relief Drain Rehabilitation programme. The work will renew large-diameter sewers between Ferndale Street and Obama Boulevard.
Key points
- Spiniello Infrastructure West won the $14,754,322 contract as the lowest of two bidders, 9.25% above the City Engineer's $13,504,588 estimate.
- The project will rehabilitate 3,309 linear feet of sewer, including 2,944 feet of 54-inch reinforced-concrete pipe, a 30-inch double-barrel cast-iron siphon and 36-inch vitrified-clay pipe.
- The programme has total funding not to exceed $15,492,038, including $737,716 in contingencies; $1,273,320 is available from the Sewer Capital Fund in fiscal year 2026-27.
- Three access pits on Mansfield Avenue will require full street closures between Ferndale Street and Jefferson Boulevard.
Full report
Los Angeles’ Board of Public Works has unanimously awarded Spiniello Infrastructure West a $14.75 million contract to rehabilitate a 3,309ft section of the Westlake Relief Drain in Council District 10.
The 730-calendar-day contract covers Unit 5 of the programme, running along Mansfield Avenue and La Brea Avenue from Ferndale Street to Obama Boulevard. The Board approved the award forthwith on 20 November.
The scope includes rehabilitation of 2,944ft of 54-inch circular reinforced-concrete sewer, 246ft of 30-inch double-barrel cast-iron siphon pipe and 119ft of 36-inch vitrified-clay pipe. Work will also rehabilitate maintenance holes and siphon inlet and outlet structures, and reconnect house connections and sewer laterals.
Staff told the Board that the sewer was constructed in 1937 and that the project is intended to address deficiencies in the wastewater collection system and avoid future emergency repairs. The project has been categorically exempted under the City’s California Environmental Quality Act guidelines.
Spiniello was the low bidder among two submissions received on 15 July. Its $14,754,322 bid was 9.25% above the City Engineer’s $13,504,588 estimate; J.R. Pipeline submitted a $16,461,038 bid. Spiniello pledged 23.95% subcontractor participation, above the project’s 20% mandatory minimum. The firm has previously undertaken numerous Board-issued contracts, with no significant or unresolved inspection, contract-compliance or bidder-responsibility issues reported by the Bureau of Contract Administration.
The approved contract award is supported by a project funding ceiling of $15.49 million, including $737,716 in contingencies. The city has identified $1.27 million from the Sewer Capital Fund for fiscal year 2026-27, with remaining funding to be budgeted in future years.
Three access pits needed for sewer rehabilitation will require full closures on Mansfield Avenue, a local street, between Ferndale Street and Jefferson Boulevard. Council District 10 and residents have been informed, and the district supported the project and concurred with peak-hour exemptions where applicable. Staff said affected parties will receive details on closures and access alternatives once construction begins.
This summary was generated by AI based on the source document and may contain errors.