Porterville approves $4m utility SCADA overhaul
City of Porterville Public Works Department, California · Meeting date: November 17, 2026 · Published: November 18, 2026
Porterville City Council has authorised a multi-year programme to replace ageing controls and communications equipment across its water, sewer and stormwater estate. The first phase will focus on lift stations, while future spending remains subject to annual appropriations.
Key points
- The $4.02 million programme, including a 10% contingency, covers 29 storm and sewer lift stations, 31 production wells, nine booster stations and seven water storage tanks.
- Council approved Telstar Instruments as sole-source SCADA integrator, subject to City Attorney confirmation of procurement authority, and authorised negotiation of a multi-year master agreement.
- Porterville has budgeted $800,000 in FY2026-27 to address up to 20 storm and sewer lift stations in the initial phase.
- Dee Jaspar & Associates found Telstar's prices consistent with comparable industry work and supported retaining a single integrator for system continuity.
Full report
Porterville City Council has approved a $4.02 million multi-year programme to modernise the supervisory control and data acquisition systems serving approximately 76 water, wastewater and stormwater facilities.
The unanimously approved programme will replace ageing control panels, programmable logic controllers and communications equipment, while bringing wells, storage tanks, booster stations and lift stations onto a centralised SCADA platform. The approved ceiling includes a 10% contingency of $365,448.70 on a base programme estimate of $3.65 million.
The estate comprises 31 active production wells, 29 stormwater and sewer lift stations, nine booster pump stations and seven water storage tanks. The 31 well upgrades account for the largest share of the base programme, at $1.81 million. Lift-station works are estimated at $1.15 million, followed by $392,499 for booster stations and $297,493 for tanks.
The city has allocated $800,000 in its FY2026-27 capital improvement budget for the first phase, anticipated to cover up to 20 stormwater and sewer lift stations. Future phases will proceed only through written work authorisations backed by available annual appropriations; the approval does not appropriate or commit the entire $4.02 million upfront.
Telstar Instruments was approved as the sole-source system integrator, subject to confirmation of the applicable procurement authority by the City Attorney. Council also authorised staff to negotiate a multi-year master agreement within the approved scope and programme maximum.
The sole-source decision builds on Telstar's work on the city’s SCADA foundation through the Well 34 project. The company completed the SCADA design and incorporated a new central SCADA computer through that work, which staff said gives Porterville an estimated $271,581 saving by avoiding duplication of the design and infrastructure.
An independent review by Dee Jaspar & Associates supported use of a single integrator, citing continuity in hardware, software and programming. The consultant compared Telstar’s $58,449 proposal for a well-site upgrade with a $64,910.22 quotation for comparable work in McFarland and concluded that Telstar’s pricing was in line with industry standards.
Telstar’s scopes include site control panels, PLC and SCADA programming, communications equipment, alarm call-outs, start-up and testing. For lift stations, the system is designed to monitor high-level alarms, motor faults, wet-well levels, power failure, running feedback and remote or automatic operating status.
The Water Utility Superintendent told the council that much of the current equipment is outdated and increasingly unreliable, requiring staff to visit facilities to check equipment and collect information that should be available remotely. The modernised platform is intended to improve remote monitoring and alarm response and identify equipment failures sooner.
A public speaker supported the capital programme but urged the council to obtain an independent cybersecurity evaluation before proceeding, citing national guidance for water and wastewater systems. The mayor said the city has a contingency plan to disconnect the system and operate manually with generators if it comes under attack, while the City Manager said the city would undertake cybersecurity due diligence with Telstar during implementation.
The council approved the programme, sole-source selection, phased approach and master-agreement negotiations on a 5-0 vote.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council Meeting, City of Porterville Public Works Department