Fort Smith approves $602m consent-decree wastewater programme
Fort Smith Utility Department, Arkansas · Meeting date: November 17, 2026 · Published: November 18, 2026
Fort Smith’s Board of Directors has authorised implementation of a $601.75 million wastewater capital improvement plan for 2027-36. The programme concentrates early spending on Massard wet-weather treatment, sewer rehabilitation and capacity upgrades required under the city’s consent decree.
Key points
- The 2027-36 consent-decree wastewater CIP totals $601,754,491 and is funded through 2025 Sales & Use Tax Bonds.
- Planned 2027 expenditure is $69.13 million, rising to $84.25 million in 2028.
- Massard Wastewater Pump Station and Wet Weather Treatment construction is allocated $37.5 million in both 2027 and 2028.
- The plan allocates up to $28 million a year for sewer assessment-area remedial repair and replacement construction from 2028 through 2036.
- Fort Smith said its 2026 consent-decree linear-foot and manhole milestones had been met and exceeded, with 2027 milestones expected to be met or exceeded by projects already under construction.
Full report
Fort Smith has approved a $601.75 million, 10-year capital programme for consent-decree wastewater works, setting out an intensive schedule of sewer rehabilitation, capacity projects and treatment-plant investment through 2036.
The Board of Directors unanimously adopted the 2027-36 Consent Decree Wastewater Capital Improvement Plan on 17 November, authorising staff to implement the programme. The plan is funded through the city’s 2025 Sales & Use Tax Bonds and is structured around consent-decree milestones that must be completed by 30 June 2038.
Expenditure is scheduled at $69.13 million in 2027 and $84.25 million in 2028, before settling into annual programmes ranging from $40.05 million to $54.55 million between 2029 and 2036.
The largest early item is a $75 million allocation over 2027 and 2028 for construction of the Massard Wastewater Pump Station and Wet Weather Treatment project, identified as Package B of the Massard Master Plan. The same facility is also a central element of Fort Smith’s separately approved non-consent-decree wastewater plan.
Sewer assessment-area rehabilitation forms the other major long-term commitment. The consent-decree CIP provides $2.5 million annually from 2027 through 2035 for design of remedial repairs and replacements covering 50,000 feet of sewer and 250 manholes. Construction funding begins at $13 million in 2027 and rises to $28 million annually from 2028 through 2036.
The programme also includes Basin 12 remedial measures, capacity upgrades in Basins FL02 and P004, and later Basin 12 Phase II works. The FL02 capacity project, described as providing a five-year level of service in an environmental-justice area, is allocated $6 million in both 2027 and 2028. Basin P004 capacity improvements receive $300,000 in 2027 and $3 million in 2028.
Pump-station work includes the South 4th and I Street Pump Station No. 9, Ball Road Pump Station No. 18, Riley Farms Pump Station No. 22 and Walnut Street Pump Station No. 5. The plan also maintains recurring funding for sewer-line televising and cured-in-place pipe work at $2.5 million annually throughout the 10-year period.
Fort Smith said it had met and exceeded 2026 consent-decree milestones for linear feet and manholes. Projects already under construction are expected to meet or exceed the city’s 2027 milestones, according to the plan.