Gilbert releases $7.38m for next North WTP delivery phases
Gilbert Utilities Department, Arizona · Meeting date: November 17, 2026 · Published: November 18, 2026
Gilbert Town Council has authorised four consultancy and preconstruction packages for the North Water Treatment Plant programme, which is expected to supply more than 70% of the town's available water at build-out. The approvals support value engineering, procurement planning and extended oversight while current treatment-process construction continues.
Key points
- Council approved $7.38 million across four North Water Treatment Plant service phases as part of its consent calendar, which passed 7-0.
- Water Works Engineers received a $4.30 million Phase 6 engineering approval, while Kennedy Jenks received $2.41 million for PM/CM services and Sundt/PCL received $608,529 for CM@R preconstruction.
- Brown and Caldwell received $65,295 for independent QA/QC reviews of contractor-developed PLC and SCADA programmes and related RFIs.
- The programme is funded through the Water Fund and Water Resources Municipal Property Corporation bonds; its WA1589 and WA1579 components are included in Gilbert's FY2027-FY2036 capital improvement plan.
Full report
Gilbert Town Council has approved $7.38 million of further professional services for the North Water Treatment Plant (NWTP) upgrades and reconstruction programme, authorising the next management, engineering and preconstruction stages for the project’s final guaranteed-maximum-price packages.
The consent-calendar approvals, passed unanimously on November 17, provide $4.30 million to Water Works Engineers for Phase 6 architect-engineer services; $2.41 million to Kennedy Jenks Consultants for Phase 5 project and construction management; and $608,529 to Sundt/PCL, a joint venture, for Phase 3 CM@R preconstruction services. Council also approved $65,295 for Brown and Caldwell under a separate NWTP SCADA and instrumentation-and-controls support project.
The NWTP treats available surface water for customers across Gilbert’s system. It supplies the majority of the town’s area through pressure zones 1, 2 and 4, and is anticipated to provide more than 70% of Gilbert’s available water supply at build-out. The wider WA1589 project began construction in 2022 and is currently in its third and fourth GMP phases.
The new engineering phase covers value-engineering work for GMPs 5 and 6, alongside extended construction administration and inspection services for GMPs 3 and 4. Its scope includes workshops, procurement and demolition packages, construction-package design, pre-sedimentation-basin work, final yard piping, site restoration, paving and Nichols Park work. The approved engineering phase carries a project-completion date of October 27, 2028.
Kennedy Jenks will provide preconstruction support for the fifth and sixth GMP packages, including independent cost estimates, review of the CM@R’s GMP proposals and subcontractor bidding oversight. It will also continue construction-management and inspection services for work already under construction in GMPs 3 and 4. Its approved phase runs through June 30, 2027.
Sundt/PCL’s preconstruction package supports the Phase 5/6 redesign through value engineering, constructability reviews, estimating, procurement planning, bid-package preparation and GMP development. The stated schedule anticipates design from November 2026 to August 2027, followed by procurement and construction through October 2028.
Brown and Caldwell’s assignment will review contractor-developed SCADA and PLC programming for the new treatment plant. Gilbert is installing Rockwell Automation’s PlantPAx SCADA system and ControlLogix PLCs, replacing the technologies currently used by the town. Brown and Caldwell will act as an owner’s agent, providing technical comments on up to nine PLC programmes, SCADA submissions and relevant RFIs; final approval remains with the engineer of record.
WA1589 is funded by the Water Fund and Water Resources Municipal Property Corporation bonds, while the WA1579 controls-support work is funded by the Water Fund.
This summary was generated by AI based on the source document and may contain errors.